ThermoFisher Scientific - Florence, SC

Architectural Contractor for spray dryer project Phase I & II

Project consisting of (2) independent spray dryer suites installed in existing 7 story API Manufacturing facility.

  • Framing, Drywall, and Insulation

  • Frames/Doors/Hardware Installation

  • Installation of various stainless-steel furnishings

  • Epoxy wall coatings

  • Design, fabricate, install stainless steel boom hoist for installation and removal of spray nozzles

  • Installation and removal of access scaffolding

  • Installation of gowning suite equipment per area classification

    • Misting showers, PAPR cabinet/charging station, Gowning accessories cabinet, Pass thrus

  • Stainless steel bumper guards and corner guards

  • Assisted client with coordination management

  • Procure and install high-speed roll up door

  • Procure and install stainless steel ceiling access doors

Pilot Plant floor replacement

Install hose storage station at truck unloading area

Various scaffolding and insulation of valves/heat exchangers/production (thermal blankets fabricated on site)

Exterior joint sealant of existing warehouse building

Contractor for Pilot Plant Platform and reactor design and relocation

  • Re-installed and refinished client supplied support platform and handrails

  • Install client supplied 200-Gal reactor vessel

Next
Next

Steven Charles Original Desserts – Pembroke, NC